15 September 2020
9 min read
#Dispute Resolution & Litigation, #Corporate & Commercial Law
Published by:
Contracts routinely contain dispute resolution clauses in which the parties record their binding preferences for the resolution of disputes. This may include referral to a particular court, or arbitration, mediation or expert determination. It may include several steps – negotiation, followed by mediation, followed by referral to court or arbitration and/or an expert.
It is not uncommon, and is perhaps understandable, that when negotiating a contract the parties tend to focus on the commercial opportunities rather than what will happen if things go wrong.
When drafting a contract, it is tempting to adopt the boilerplate dispute resolution clause at hand. However, a poorly drafted clause will do little to solve issues and may actually become the cause of further time consuming and costly dispute.
This has been demonstrated in a series of cases recently determined by the NSW Supreme Court of Appeal where the terms of dispute resolution clauses themselves were the subject of dispute. The cases demonstrate, as President Andrew Bell acknowledged, that:
“Dispute resolution clauses may be crafted and drafted in an almost infinite variety of ways and styles…and are just as capable of generating litigation as any other contractual clause.”
Unfortunately, parties to commercial contracts often do not pre-empt this and do not pay enough attention to the dispute resolution clauses in their agreements, leading to, as Bell P references, “commercial nonsense”. How does one avoid such commercial nonsense? A study of recent court decisions provides guidance.
Exclusive jurisdiction clauses – Australian Health & Nutrition Association Ltd v Hive Marketing Group Pty Ltd [2019] NSWCA 61
The facts of this case are as follows:
Sanitarium and Rebel were granted leave to appeal the decision. The question before the Court was whether the exclusive jurisdiction clause should be enforced in circumstances where not all parties to the current proceeding were parties to the clause.
Bell P noted that there was high desirability that all aspects of a dispute should be resolved in the one place to ensure tidiness and most importantly, to minimise the possibility of different courts reaching different decisions on the same issue – a consequence that could undermine confidence in the rule of law.
Ultimately, the Court ruled that the importance of holding parties to their bargain, even if not all parties were privy to such a bargain, outweighed the risk of a multiplicity of proceedings. Bell P stated that whilst Rebel was not a party to the exclusive jurisdiction clause, it must have at least been aware of it and that the proceedings were rightfully stayed.
Arbitration – Inghams Enterprises Pty Limited v Hannigan [2020] NSWCA 82
The facts of this case are as follows:
As to the waiver issue, the Court held that Mr Hannigan had not waived his rights to arbitration.
As to the construction issue, the bench was divided. Meagher and Gleeson JJA held that the claim for unliquidated damages was not a claim for an amount payable or owed under any express or implied terms of the Agreement, instead, it arose from common law principles. Thus, the Court held that the dispute did not fall within the clause and was not one which could be submitted to arbitration.
However, Bell P stated that a liberal approach should be applied towards the construction of the dispute resolution clause. The entire clause should be interpreted in light of the context of the agreement. Thus, Bell P found terms, such as “any”, indicated that the parties intended for the clause to have a wide scope. Further, he asserted that a secondary obligation to pay damages arises from or under the contract just as much as a primary obligation and consequently found that the claim for unliquidated damages fell within the ambit of clause 23.
Expert determination – Lepcanfin Pty Ltd v Lepfin Pty Ltd [2020] NSWCA 155
The facts of this case are as follows:
Lepcanfin’s leave to appeal the Guarantee issue was refused. The Court held that the claims for relief arose out of the Deed and the parties should be held to their bargain.
Leave to appeal the question of the mandate was granted but the appeal was ultimately dismissed. Bell P stated that the expert determination clause should be interpreted broadly as seeking to have all aspects of the commercial arrangements resolved by expert determination. This included removing the right of a party to enjoy the benefit of a contractual provision where it is properly characterised as a penalty. The EDA was also said to be a brief description of the subject matter of dispute, rather than a limitation on the matters to be determined. Thus, the Court found that the Expert had clearly acted within her mandate in resolving the penalty issue.
This case was a clear example, as Bell P stated (citing The Illawarra Community Housing Trust Limited v MP Park Lane Pty Ltd [2020] NSWSC 751) that an expert determination clause will not oust the jurisdiction of the court. Even a well-drafted dispute resolution clause may become the subject of dispute.
Lessons learned – think ‘ART’
These decisions serve as reminders to parties to familiarise themselves with dispute resolution clauses both in agreements that they are party to, and also potentially those they are not party to but which may still affect their interests.
As a helpful reminder, parties should consider A-R-T when looking at dispute clauses
Is the clause:
Authors: Geoff Farnsworth & Ushna Bashir
Disclaimer
The information in this publication is of a general nature and is not intended to address the circumstances of any particular individual or entity. Although we endeavour to provide accurate and timely information, we do not guarantee that the information in this newsletter is accurate at the date it is received or that it will continue to be accurate in the future.
Published by: